Title: 2GR-FKS (STARTING): STARTER: INSTALLATION; 2019 - 2022 MY Avalon [04/2018 - ] |
INSTALLATION
PROCEDURE
1. INSTALL STARTER ASSEMBLY
(a) Install the starter assembly with the 2 bolts.
Torque:
46 N·m {469 kgf·cm, 34 ft·lbf}
(b) Connect the engine wire to the terminal 30 with the nut.
Torque:
9.8 N·m {100 kgf·cm, 87 in·lbf}
(c) Close the terminal cap.
(d) Connect the starter assembly connector.
2. INSTALL BATTERY CLAMP SUB-ASSEMBLY
Click here
3. INSTALL ECM
Click here
4. INSTALL AIR CLEANER ASSEMBLY WITH AIR CLEANER HOSE
Click here
5. INSTALL INLET AIR CLEANER ASSEMBLY
Click here
6. INSTALL V-BANK COVER SUB-ASSEMBLY
Click here
7. INSTALL COOL AIR INTAKE DUCT SEAL
Click here
8. INSTALL BATTERY