Last Modified: 08-21-2023 6.11:8.1.0 Doc ID: RM100000001AY14
Model Year Start: 2019 Model: Avalon HV Prod Date Range: [04/2018 - 08/2020]
Title: INTERIOR PANELS / TRIM: FRONT CONSOLE BOX: INSTALLATION; 2019 - 2020 MY Avalon Avalon HV [04/2018 - 08/2020]

INSTALLATION

PROCEDURE

1. INSTALL CONSOLE ASSEMBLY

(a) Engage the 2 clips as shown in the illustration.

Install in this Direction

(b) Install the console box assembly with the 4 bolts and 2 screws.

(c) Connect the 2 connectors.

2. INSTALL UPPER FRONT CONSOLE PANEL SUB-ASSEMBLY

(a) Engage the clamp and connect the connector.

(b) Engage the 4 clips as shown in the illustration to install the upper front console panel sub-assembly.

Install in this Direction

3. INSTALL CONSOLE BOX BEZEL

(a) Connect the connector.

(b) Engage the 6 clips as shown in the illustration to install the console box bezel.

Install in this Direction

4. INSTALL INSTRUMENT PANEL FINISH PANEL END LH

(a) Engage the guide, 2 claws and clip as shown in the illustration to install the instrument panel finish panel end LH.

Install in this Direction

5. INSTALL REAR UPPER CONSOLE PANEL SUB-ASSEMBLY

(a) Connect the 2 connectors.

(b) Engage the 7 clips as shown in the illustration to install the rear upper console panel sub-assembly.

Install in this Direction

6. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY

for Gasoline Model: Click here 2019 - 2022 MY Avalon [04/2018 -        ]; UA80E (AUTOMATIC TRANSMISSION / TRANSAXLE): SHIFT LEVER KNOB: INSTALLATION+

for HV Model: Click here 2019 - 2022 MY Avalon HV [04/2018 -        ]; P710 (HYBRID TRANSMISSION / TRANSAXLE): SHIFT LEVER KNOB: INSTALLATION+

7. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY

(a) Engage the 2 guides and 2 clips as shown in the illustration.

Install in this Direction

(b) Install the center instrument cluster finish panel sub-assembly with the 4 screws.

8. INSTALL CONSOLE BOX POCKET SUB-ASSEMBLY

(a) Engage the 12 clips as shown in the illustration to install the console box pocket sub-assembly.

Install in this Direction (1)

Install in this Direction (2)

9. INSTALL FRONT CONSOLE UPPER PANEL GARNISH

(a) Engage the 2 clamps and connect the 4 connectors.

(b) Engage the 6 clips as shown in the illustration to install the front console upper panel garnish.

Install in this Direction

10. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL RH

(a) Engage the 8 clips as shown in the illustration to install the lower instrument panel finish panel RH.

Install in this Direction

11. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL LH

(a) Engage the 9 clips as shown in the illustration to install the lower instrument panel finish panel LH.

Install in this Direction

12. INSTALL CONSOLE BOX CARPET

(a) Install the console box carpet.

13. INSTALL CONSOLE BOX POCKET

(a) Install the console box pocket.