INSTALLATION
PROCEDURE
1. INSTALL POWER MANAGEMENT CONTROL ECU
(a) Engage the 2 claws and install the power management control ECU.
2. INSTALL ECU INTEGRATION BOX RH
3. INSTALL GLOVE COMPARTMENT DOOR SUB-ASSEMBLY
4. INSTALL COWL SIDE TRIM BOARD RH
5. INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP RH
6. INSTALL DOOR SCUFF PLATE ASSEMBLY RH
7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque:
5.4 N·m {55 kgf·cm, 48 in·lbf}
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page
).
|